The project has been completed. These are the final project photos; additional road closures will be added if necessary.
Schedule
Previous Updates:
Work Completed in March 2024
-
Complete CL-6 permanent fence installation.
-
Complete RW gutter and slope paving.
-
Complete installation of cable railing on top of retaining walls.
-
Complete installation of McKinley structural section at Daniels intersection.
-
Complete JPCP installation on all four ramps with profile and grind.
-
Continue hydroseed installation on all ramp slopes.
-
Continue installation of fiber rolls on ramp slopes.
-
Continue drainage system installations.
-
Continue traffic signal electrical installation.
-
Continue installation of ramp metering loops.
-
Continue SWPPP BMP maintenance and implementation at all locations on the project site.
-
Begin HMA installation on McKinley.
-
Begin installation of permanent roadside signs.
-
Begin final pavement striping and marking on MC1-4 and McKinley.
-
Begin restripe of SR 120.
Work Completed in Feburary 2024
-
Completed form and pour of concrete curb and gutter along McKinley.
-
Completed PCC dike installation on all ramps.
-
Completed installation of OHSS 1.
-
Completed CL-6 temporary fence removals.
-
Continued JPCP installation on all four ramps.
-
Continued CL-6 permanent fence installation.
-
Continued hydroseed installation on all ramp slopes.
-
Continued installation of fiber rolls on ramp slopes.
-
Continued drainage system installations.
-
Continued traffic signal electrical installation.
-
Continued installation of ramp metering loops.
-
Continued SWPPP BMP maintenance and implementation at all locations on the project site.
-
Continued RW gutter and slope paving.
-
Continued installation of McKinley structural section at Daniels intersection.
-
Began installation of cable railing on top of retaining walls.
Work Completed in January 2024
-
Completed metal beam guardrail installation on all ramps.
-
Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.
-
Continued AB and geogrid placement in McKinley structural section.
-
Continued CL-6 fence installation and maintenance, including grubbing activities for temp fence removals.
-
Continued hydroseed installation on all ramp slopes.
-
Continued installation of temporary fiber rolls on ramp slopes.
-
Continued drainage system installations.
-
Continued traffic signal electrical installation.
-
Continued installation of ramp metering loops.
-
Continued SWPPP BMP maintenance and implementation at all locations on the project site.
-
Continued form and pour of concrete curb and gutter along McKinley.
Work Completed in December 2023
-
Completed RW rebar and structural concrete installation.
-
Continued drainage system installations.
-
Continued traffic signal electrical installation.
-
Continued installation of ramp metering loops.
-
Continued SWPPP BMP maintenance and implementation at all locations on the project site.
-
Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.
-
Continued CL-6 fence installation and maintenance, including grubbing activities for temp fence removals.
-
Continued hydroseed installation on all ramp slopes.
-
Continued installation of temporary fiber rolls on ramp slopes.
-
Continued form and pour of concrete curb and gutter along McKinley.
-
Began metal beam guardrail installation on all ramps.
-
Began AB and geogrid placement in McKinley structural section.
Work Completed in November 2023
-
Completed HMA installation at the SR 120 tie-in locations.
-
Continued drainage system installations.
-
Continued rebar installation and form and pour for CIP wall.
-
Continued traffic signal electrical installation.
-
Continued installation of ramp metering loops.
-
Continued SWPPP BMP maintenance and implementation at all locations on the project site.
-
Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.
-
Continued CL-6 fence installation and maintenance, including grubbing activities for fence removals.
-
Continued installation of temporary fiber rolls on ramp slopes.
-
Continued hydroseed installation on all ramp slopes.
-
Began form and pour of concrete curb and gutter along McKinley.
Work Completed in October 2023
-
Complete relocation of 36” City of Manteca effluent waterline.
-
Complete installation of 12” water line through McKinley.
-
Complete installation of temporary fiber rolls and permanent compost socks on ramp slopes.
-
Continue drainage installations at various locations.
-
Continue construction of new retaining walls at the McKinley Avenue UC.
-
Continue JPCP installation on all SR 120 on/off ramps from McKinley avenue.
-
Continue SWPPP BMP maintenance and implementation.
-
Begin traffic signal electrical installation.
-
Completed 36" effluent line installation, including testing and tie-ins.
-
Installed OHSSs.
-
Continued HMA installation at the SR 120 tie-in locations.
-
Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.
-
Continued installation of rebar for CIP wall.
-
Continued CL-6 fence installation and maintenance, including grubbing activites for fence removals.
-
Continued installation of temporary fiber rolls on ramp slopes.
-
Continued drainage system installations.
-
Continued SWPPP BMP maintenance and implementation at all locations on the project site.
-
Began form and pour for CIP walls.
-
Began installation of ramp metering loops.
-
Began traffic signal electrical installation.
-
Began hydroseed installation on all ramp slopes.
Work Completed in September 2023
-
Completed roadway ATPB/HMA section construction for all SR 120 on/off ramps from McKinley avenue.
-
Continued relocation of 36” City of Manteca effluent waterline.
-
Continued drainage installations at various locations.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued construction of new retaining walls at the McKinley Avenue UC.
-
Began JPCP installation on all SR 120 on/off ramps from McKinley avenue.
-
Completed roadway ATPB/HMA section construction for all SR 120 on/off ramps from McKinley avenue.
-
Continued relocation of 36” City of Manteca effluent waterline.
-
Continued drainage installations at various locations.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued construction of new retaining walls at the McKinley Avenue UC.
-
Began JPCP installation on all SR 120 on/off ramps from McKinley avenue.
Work Completed in August 2023
-
Continued relocation of 36” City of Manteca effluent waterline.
-
Continued drainage installations at various locations.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued roadway structural section construction for all SR 120 on/off ramps from McKinley avenue.
-
Completed structure excavation for new retaining walls at the McKinley Avenue UC.
-
Completed installation of nested guardrail to allow for continued installation of drainage systems.
-
Continued construction of new retaining walls at the McKinley Avenue UC.
Work Completed in July 2023
-
Completed installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.
-
Completed structure excavation for new retaining walls at the McKinley Avenue UC.
-
Completed electrical installations at various locations.
-
Continued drainage installations at various locations.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued roadway structural section construction for all SR 120 on/off ramps from McKinley avenue.
-
Began relocation of 36” City of Manteca effluent waterline.
Work Completed in June 2023
-
Completed embankment construction on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.
-
Completed embankment construction on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.
-
Completed embankment construction on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.
-
Continued structure excavation for new retaining walls at the McKinley Avenue UC.
-
Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.
-
Continued drainage installations at various locations.
-
Continued SWPPP BMP maintenance and implementation.
Work Completed in May 2023
-
Continued structure excavation for new retaining walls at the McKinley Avenue UC.
-
Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.
-
Continued embankment construction on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.
-
Continued embankment construction on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.
-
Continued embankment construction on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.
-
Continued drainage installations at various locations.
-
Continued SWPPP BMP maintenance and implementation
Work Completed in April 2023
-
Completed emergency erosion repairs to EB SR 120 (Caltrans).
-
Continued structure excavation for new retaining walls at the McKinley Avenue UC.
-
Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.
-
Continued Comcast and Frontier utility relocations.
-
Continued SWPPP BMP maintenance and implementation.
Work Completed in March 2023
-
Continued Comcast and Frontier utility relocations.
-
Continued SWPPP BMP maintenance and implementation.
-
Began emergency erosion repairs to EB SR 120 (Caltrans).
Work Completed in February 2023
-
Completed excavation and backfill of the joint trench for Comcast and Frontier utility relocations.
-
Continued SWPPP BMP maintenance and implementation.
Work Completed in January 2023
-
Completed placement of traffic control devices on EB SR 120 for work zone positive protection.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued drainage installations at various locations.
Work Completed in December 2022
-
Completed placement of traffic control devices on WB SR 120 for work zone positive protection.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued drainage installations at various locations.
-
Continued structure excavation for new retaining walls at the McKinley Avenue UC.
-
Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.
Work Completed in November 2022
-
Continued SWPPP BMP maintenance and implementation.
-
Continued drainage installations at various locations.
-
Continued structure excavation for new retaining walls at the McKinley Avenue UC.
-
Began installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue
Work Completed in October 2022
-
Completed cut-to-fill earthwork activities on the "MC1" line for the future WB SR 120 off-ramp to McKinley Avenue.
-
Completed cut-to-fill earthwork activities on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.
-
Completed cut-to-fill earthwork activities on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.
-
Completed cut-to-fill earthwork activities on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.
-
Completed embankment construction on the "MC1" line for the future WB SR 120 off-ramp to McKinley Avenue.
-
Continued SWPPP BMP maintenance and implementation.
-
Continued embankment construction on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.
-
Continued embankment construction on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.
-
Continued embankment construction on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.
-
Began drainage installation at various locations.
Work Completed in September 2022
-
Completed clearing activities and the installation of SWPPP BMPs, TFESA, temporary fencing, and construction area signage.
-
Continued SWPPP BMP maintenance and implementation.
-
Began cut-to-fill earthwork activities and import borrow on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.
-
Began cut-to-fill earthwork activities on the "MC1" line for the future WB SR 120 off-ramp to McKinley Avenue.
-
Began cut-to-fill earthwork activities on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.