The project has been completed. These are the final project photos; additional road closures will be added if necessary.

1000006934.jpg
1000006936.jpg
1000006933.jpg
1000006931.jpg
1000006935.jpg
1000006930.jpg

Schedule

Previous Updates:

Work Completed in March 2024

  • Complete CL-6 permanent fence installation.

  • Complete RW gutter and slope paving. 

  • Complete installation of cable railing on top of retaining walls.

  • Complete installation of McKinley structural section at Daniels intersection.

  • Complete JPCP installation on all four ramps with profile and grind.

  • Continue hydroseed installation on all ramp slopes. 

  • Continue installation of fiber rolls on ramp slopes. 

  • Continue drainage system installations. 

  • Continue traffic signal electrical installation. 

  • Continue installation of ramp metering loops.

  • Continue SWPPP BMP maintenance and implementation at all locations on the project site.  

  • Begin HMA installation on McKinley.

  • Begin installation of permanent roadside signs.

  • Begin final pavement striping and marking on MC1-4 and McKinley.

  • Begin restripe of SR 120.

 

Work Completed in Feburary 2024

  • Completed form and pour of concrete curb and gutter along McKinley. 

  • Completed PCC dike installation on all ramps.

  • Completed installation of OHSS 1.

  • Completed CL-6 temporary fence removals.

  • Continued JPCP installation on all four ramps.

  • Continued CL-6 permanent fence installation.

  • Continued hydroseed installation on all ramp slopes. 

  • Continued installation of fiber rolls on ramp slopes. 

  • Continued drainage system installations. 

  • Continued traffic signal electrical installation. 

  • Continued installation of ramp metering loops.

  • Continued SWPPP BMP maintenance and implementation at all locations on the project site.  

  • Continued RW gutter and slope paving. 

  • Continued installation of McKinley structural section at Daniels intersection.

  • Began installation of cable railing on top of retaining walls.

Work Completed in January 2024

  • Completed metal beam guardrail installation on all ramps. 

  • Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.

  • Continued AB and geogrid placement in McKinley structural section.

  • Continued CL-6 fence installation and maintenance, including grubbing activities for temp fence removals. 

  • Continued hydroseed installation on all ramp slopes. 

  • Continued installation of temporary fiber rolls on ramp slopes. 

  • Continued drainage system installations. 

  • Continued traffic signal electrical installation. 

  • Continued installation of ramp metering loops.

  • Continued SWPPP BMP maintenance and implementation at all locations on the project site.  

  • Continued form and pour of concrete curb and gutter along McKinley.

Work Completed in December 2023

  • Completed RW rebar and structural concrete installation.

  • Continued drainage system installations. 

  • Continued traffic signal electrical installation. 

  • Continued installation of ramp metering loops.

  • Continued SWPPP BMP maintenance and implementation at all locations on the project site.  

  • Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels. 

  • Continued CL-6 fence installation and maintenance, including grubbing activities for temp fence removals. 

  • Continued hydroseed installation on all ramp slopes. 

  • Continued installation of temporary fiber rolls on ramp slopes. 

  • Continued form and pour of concrete curb and gutter along McKinley. 

  • Began metal beam guardrail installation on all ramps. 

  • Began AB and geogrid placement in McKinley structural section.

Work Completed in November 2023 

  • Completed HMA installation at the SR 120 tie-in locations.

  • Continued drainage system installations.

  • Continued rebar installation and form and pour for CIP wall. 

  • Continued traffic signal electrical installation.

  • Continued installation of ramp metering loops.

  • Continued SWPPP BMP maintenance and implementation at all locations on the project site.

  • Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.

  • Continued CL-6 fence installation and maintenance, including grubbing activities for fence removals.

  • Continued installation of temporary fiber rolls on ramp slopes.

  • Continued hydroseed installation on all ramp slopes.

  • Began form and pour of concrete curb and gutter along McKinley.

Work Completed in October 2023 

  • Complete relocation of 36” City of Manteca effluent waterline.

  • Complete installation of 12” water line through McKinley.

  • Complete installation of temporary fiber rolls and permanent compost socks on ramp slopes. 

  • Continue drainage installations at various locations.

  • Continue construction of new retaining walls at the McKinley Avenue UC.

  • Continue JPCP installation on all SR 120 on/off ramps from McKinley avenue. 

  • Continue SWPPP BMP maintenance and implementation.

  • Begin traffic signal electrical installation.

  • Completed 36" effluent line installation, including testing and tie-ins. 

  • Installed OHSSs.

  • Continued HMA installation at the SR 120 tie-in locations.

  • Continued JPCP installation on all four ramps, including setting epoxy dowel baskets and drilling and bonding dowels.

  • Continued installation of rebar for CIP wall.

  • Continued CL-6 fence installation and maintenance, including grubbing activites for fence removals.

  • Continued installation of temporary fiber rolls on ramp slopes.

  • Continued drainage system installations.

  • Continued SWPPP BMP maintenance and implementation at all locations on the project site.

  • Began form and pour for CIP walls.

  • Began installation of ramp metering loops.

  • Began traffic signal electrical installation.

  • Began hydroseed installation on all ramp slopes.

Work Completed in September 2023 

  • Completed roadway ATPB/HMA section construction for all SR 120 on/off ramps from McKinley avenue.

  • Continued relocation of 36” City of Manteca effluent waterline.

  • Continued drainage installations at various locations.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued construction of new retaining walls at the McKinley Avenue UC.

  • Began JPCP installation on all SR 120 on/off ramps from McKinley avenue. 

  • Completed roadway ATPB/HMA section construction for all SR 120 on/off ramps from McKinley avenue.

  • Continued relocation of 36” City of Manteca effluent waterline.

  • Continued drainage installations at various locations.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued construction of new retaining walls at the McKinley Avenue UC.

  • Began JPCP installation on all SR 120 on/off ramps from McKinley avenue. 

Work Completed in August 2023

  • Continued relocation of 36” City of Manteca effluent waterline.

  • Continued drainage installations at various locations.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued roadway structural section construction for all SR 120 on/off ramps from McKinley avenue.  

  • Completed structure excavation for new retaining walls at the McKinley Avenue UC.

  • Completed installation of nested guardrail to allow for continued installation of drainage systems.

  • Continued construction of new retaining walls at the McKinley Avenue UC.

Work Completed in July 2023

  • Completed installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.

  • Completed structure excavation for new retaining walls at the McKinley Avenue UC.

  • Completed electrical installations at various locations.

  • Continued drainage installations at various locations.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued roadway structural section construction for all SR 120 on/off ramps from McKinley avenue.  

  • Began relocation of 36” City of Manteca effluent waterline.

Work Completed in June 2023

  • Completed embankment construction on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.  

  • Completed embankment construction on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.  

  • Completed embankment construction on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.  

  • Continued structure excavation for new retaining walls at the McKinley Avenue UC.

  • Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.

  • Continued drainage installations at various locations.

  • Continued SWPPP BMP maintenance and implementation.

Work Completed in May 2023

  • Continued structure excavation for new retaining walls at the McKinley Avenue UC.

  • Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.

  • Continued embankment construction on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.  

  • Continued embankment construction on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.  

  • Continued embankment construction on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.  

  • Continued drainage installations at various locations.

  • Continued SWPPP BMP maintenance and implementation

Work Completed in April 2023

  • Completed emergency erosion repairs to EB SR 120 (Caltrans).

  • Continued structure excavation for new retaining walls at the McKinley Avenue UC.

  • Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.

  • Continued Comcast and Frontier utility relocations.

  • Continued SWPPP BMP maintenance and implementation.

Work Completed in March 2023

  • Continued Comcast and Frontier utility relocations.

  • Continued SWPPP BMP maintenance and implementation.

  • Began emergency erosion repairs to EB SR 120 (Caltrans).

Work Completed in February 2023

  • Completed excavation and backfill of the joint trench for Comcast and Frontier utility relocations.

  • Continued SWPPP BMP maintenance and implementation.

Work Completed in January 2023

  • Completed placement of traffic control devices on EB SR 120 for work zone positive protection.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued drainage installations at various locations.

Work Completed in December 2022

  • Completed placement of traffic control devices on WB SR 120 for work zone positive protection.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued drainage installations at various locations.

  • Continued structure excavation for new retaining walls at the McKinley Avenue UC.

  • Continued installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue UC.

Work Completed in November 2022

  • Continued SWPPP BMP maintenance and implementation.

  • Continued drainage installations at various locations.

  • Continued structure excavation for new retaining walls at the McKinley Avenue UC.

  • Began installation of ground anchors and soil nails for new retaining walls at the McKinley Avenue 

Work Completed in October 2022

  • Completed cut-to-fill earthwork activities on the "MC1" line for the future WB SR 120 off-ramp to McKinley Avenue.

  • Completed cut-to-fill earthwork activities on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.

  • Completed cut-to-fill earthwork activities on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.

  • Completed cut-to-fill earthwork activities on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.

  • Completed embankment construction on the "MC1" line for the future WB SR 120 off-ramp to McKinley Avenue.

  • Continued SWPPP BMP maintenance and implementation.

  • Continued embankment construction on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.

  • Continued embankment construction on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.

  • Continued embankment construction on the "MC4" line for the future EB SR 120 on-ramp from McKinley Avenue.

  • Began drainage installation at various locations.

Work Completed in September 2022

  • Completed clearing activities and the installation of SWPPP BMPs, TFESA, temporary fencing, and construction area signage.

  • Continued SWPPP BMP maintenance and implementation.

  • Began cut-to-fill earthwork activities and import borrow on the "MC3" line for the future EB SR 120 off-ramp to McKinley Avenue.  

  • Began cut-to-fill earthwork activities on the "MC1" line for the future WB SR 120 off-ramp to McKinley Avenue.

  • Began cut-to-fill earthwork activities on the "MC2" line for the future WB SR 120 on-ramp from McKinley Avenue.